Questions on Projects Under Construction
Submit any questions you have on projects under construction. The planner over the area will answer the question as quickly as they can.
-
Share Construction has begun on something in the open field in the southeast corner of the intersection of 2100 N and Redwood road (at least a small road is being built). What is the plan for this area? on Facebook Share Construction has begun on something in the open field in the southeast corner of the intersection of 2100 N and Redwood road (at least a small road is being built). What is the plan for this area? on Twitter Share Construction has begun on something in the open field in the southeast corner of the intersection of 2100 N and Redwood road (at least a small road is being built). What is the plan for this area? on Linkedin Email Construction has begun on something in the open field in the southeast corner of the intersection of 2100 N and Redwood road (at least a small road is being built). What is the plan for this area? link
Construction has begun on something in the open field in the southeast corner of the intersection of 2100 N and Redwood road (at least a small road is being built). What is the plan for this area?
drb asked about 1 month agoA commercial development will be going into the area. Currently, the only project approved for the area is a vet clinic, which is what has started construction. The rest of the area will develop over time, but nothing official has been submitted to the City yet.
-
Share What is timeline for finishing the sidewalks (accessibility ramps) on 2600 N? School has started. How are the kids supposed to walk to Eagle Crest Elementary. What is the city’s plan for keeping the kids safe? How long does this very dangerous situation have to go on? 2600 N has been torn up for the gas line for a year! When will they finally finish? on Facebook Share What is timeline for finishing the sidewalks (accessibility ramps) on 2600 N? School has started. How are the kids supposed to walk to Eagle Crest Elementary. What is the city’s plan for keeping the kids safe? How long does this very dangerous situation have to go on? 2600 N has been torn up for the gas line for a year! When will they finally finish? on Twitter Share What is timeline for finishing the sidewalks (accessibility ramps) on 2600 N? School has started. How are the kids supposed to walk to Eagle Crest Elementary. What is the city’s plan for keeping the kids safe? How long does this very dangerous situation have to go on? 2600 N has been torn up for the gas line for a year! When will they finally finish? on Linkedin Email What is timeline for finishing the sidewalks (accessibility ramps) on 2600 N? School has started. How are the kids supposed to walk to Eagle Crest Elementary. What is the city’s plan for keeping the kids safe? How long does this very dangerous situation have to go on? 2600 N has been torn up for the gas line for a year! When will they finally finish? link
What is timeline for finishing the sidewalks (accessibility ramps) on 2600 N? School has started. How are the kids supposed to walk to Eagle Crest Elementary. What is the city’s plan for keeping the kids safe? How long does this very dangerous situation have to go on? 2600 N has been torn up for the gas line for a year! When will they finally finish?
MWalker asked 4 months agoPedestrian ramps at intersections along 2600 N are being corrected to meet standards. Crews will be reinstalling them between Wed 8/13 and Fri 8/15 this week and may have some to finish next week as well. Children should carefully walk around these areas until they are complete. Crossing guards will be in their usual positions to help kids cross.
Crews will be milling and overlaying the asphalt surface on 2600 N between Sunset Dr and 300 W starting on Mon 8/19 and should be finished by the end of the week. Children should be careful to stay out of the roadway and away from equipment. Parents should consider walking with their kids, or designate one parent to walk all of the neighborhoods kids. They might also consider driving their kids to the end of the construction area.
Here is a link to the Embridge project on their website:
Gas Feeder Line 26 | Projects | Enbridge Gas https://share.google/ll51Tp2RRwc7akKJ3
It would be best to contact them directly for their schedule.
-
Share Hi, I am wondering about the construction along 1200 E. Start time was June 18th but when is expected to be finished? And, what work is being done? Thanks! on Facebook Share Hi, I am wondering about the construction along 1200 E. Start time was June 18th but when is expected to be finished? And, what work is being done? Thanks! on Twitter Share Hi, I am wondering about the construction along 1200 E. Start time was June 18th but when is expected to be finished? And, what work is being done? Thanks! on Linkedin Email Hi, I am wondering about the construction along 1200 E. Start time was June 18th but when is expected to be finished? And, what work is being done? Thanks! link
Hi, I am wondering about the construction along 1200 E. Start time was June 18th but when is expected to be finished? And, what work is being done? Thanks!
Lchristensen asked 6 months agoThere has been Enbridge Gas Line being installed. Here is a link to the project on their website:
Gas Feeder Line 26 | Projects | Enbridge Gas https://share.google/ll51Tp2RRwc7akKJ3
There is not a finish date on the website. You might have to contact Enbridge directly for that.
-
Share Glad to see the SR-92/N Center St intersection opened. Appreciate the explanation regarding the delay. Question: What is the project just starting on the Northwest corner if that intersection? Thanks. on Facebook Share Glad to see the SR-92/N Center St intersection opened. Appreciate the explanation regarding the delay. Question: What is the project just starting on the Northwest corner if that intersection? Thanks. on Twitter Share Glad to see the SR-92/N Center St intersection opened. Appreciate the explanation regarding the delay. Question: What is the project just starting on the Northwest corner if that intersection? Thanks. on Linkedin Email Glad to see the SR-92/N Center St intersection opened. Appreciate the explanation regarding the delay. Question: What is the project just starting on the Northwest corner if that intersection? Thanks. link
Glad to see the SR-92/N Center St intersection opened. Appreciate the explanation regarding the delay. Question: What is the project just starting on the Northwest corner if that intersection? Thanks.
fastbasset492 asked 4 months agoYes, that is a project called Sky View West Anchor.
-
Share Why has the tiny intersection at N Center St and Timpanogos Hwy been a “project” since 2019, and under construction for over a year and it’s still not done? I’ve seen miles of Bangerter Hwy completed in a fraction of the time. For those of us that live in traverse right near that intersection, we have been dealing with the construction for way too long and still can’t use it to drop my kids at both the High school and Viewpoint middle. The pick up and drop off for Viewpoint middle has been a nightmare for years because of 1 small road we’re all forced to use. School starts in 3 weeks, are we going for a 3rd school year with no access? on Facebook Share Why has the tiny intersection at N Center St and Timpanogos Hwy been a “project” since 2019, and under construction for over a year and it’s still not done? I’ve seen miles of Bangerter Hwy completed in a fraction of the time. For those of us that live in traverse right near that intersection, we have been dealing with the construction for way too long and still can’t use it to drop my kids at both the High school and Viewpoint middle. The pick up and drop off for Viewpoint middle has been a nightmare for years because of 1 small road we’re all forced to use. School starts in 3 weeks, are we going for a 3rd school year with no access? on Twitter Share Why has the tiny intersection at N Center St and Timpanogos Hwy been a “project” since 2019, and under construction for over a year and it’s still not done? I’ve seen miles of Bangerter Hwy completed in a fraction of the time. For those of us that live in traverse right near that intersection, we have been dealing with the construction for way too long and still can’t use it to drop my kids at both the High school and Viewpoint middle. The pick up and drop off for Viewpoint middle has been a nightmare for years because of 1 small road we’re all forced to use. School starts in 3 weeks, are we going for a 3rd school year with no access? on Linkedin Email Why has the tiny intersection at N Center St and Timpanogos Hwy been a “project” since 2019, and under construction for over a year and it’s still not done? I’ve seen miles of Bangerter Hwy completed in a fraction of the time. For those of us that live in traverse right near that intersection, we have been dealing with the construction for way too long and still can’t use it to drop my kids at both the High school and Viewpoint middle. The pick up and drop off for Viewpoint middle has been a nightmare for years because of 1 small road we’re all forced to use. School starts in 3 weeks, are we going for a 3rd school year with no access? link
Why has the tiny intersection at N Center St and Timpanogos Hwy been a “project” since 2019, and under construction for over a year and it’s still not done? I’ve seen miles of Bangerter Hwy completed in a fraction of the time. For those of us that live in traverse right near that intersection, we have been dealing with the construction for way too long and still can’t use it to drop my kids at both the High school and Viewpoint middle. The pick up and drop off for Viewpoint middle has been a nightmare for years because of 1 small road we’re all forced to use. School starts in 3 weeks, are we going for a 3rd school year with no access?
Traverse asked 5 months agoThe work at Center St and Timpanogos Hwy will be completed this coming week with the north leg of the intersection fully opened. All that remains is configuring the traffic signal controller and activating the new signal components. This will give much needed relief to Viewpoint Middle School traffic with school starting on August 13th.
The initial difficultly was coming to agreement about what should be done and who would pay for what between DR Horton, Lehi City, and UDOT. An agreement was finally reached and DR Horton selected a separate contractor to do the north side of Timpanogos Hwy and one to do the south side in June of 2024. The intent was for all the work to be completed before school started in August 2024.
However, there are two large aqueducts on the south side of Timpanogos Hwy for which we needed permits to do work in their easements. The one south of the commuter lanes came easily but the one between the commuter lanes and Timpanogos Hwy proper did not. There were long waiting times in getting responses and they required design changes. These delays caused the southside contractor to move on to other work. The work on the northside moved forwarded and was completed in the fall of 2024.
We were able to work through permitting through the fall and winter of 2024 and the traffic signal adjustments were installed. We looked into opening the north leg at that time but UDOT wouldn't allow the striping to be done in Timpanogos Hwy because it required concrete grinding equipment which is cooled by water. They worried it could freeze and create a hazard. They also worried about the north/south lanes being misaligned by 3 or 4 feet.
Work on southside road widening was expected to be completed by mid-May and then mid-June and now we're at the end of July. They ran into a difficult issue with a storm drain box and also had difficulties in scheduling subcontractors for such a small project. Contractors tend to prioritize their schedules for their larger projects over the small ones.
It has been a very difficult project. We are very happy that it is almost complete. We appreciate your understanding.
-
Share Hi! I was just wondering when the new section of Hudson Way is going to be finished. (Here's a pin to the section I'm talking about: https://maps.app.goo.gl/ENYnAsavKiR1JM1o6). It's the section of road that connects the homes north of 2100 North to the warehouses. I saw that some traffic signals were added at the intersection of Hudson and Redwood and there seems to be some other work occurring but couldn't find any info about this on your website. Let me know if I can provide any further details to explain the area I'm describing! Thanks on Facebook Share Hi! I was just wondering when the new section of Hudson Way is going to be finished. (Here's a pin to the section I'm talking about: https://maps.app.goo.gl/ENYnAsavKiR1JM1o6). It's the section of road that connects the homes north of 2100 North to the warehouses. I saw that some traffic signals were added at the intersection of Hudson and Redwood and there seems to be some other work occurring but couldn't find any info about this on your website. Let me know if I can provide any further details to explain the area I'm describing! Thanks on Twitter Share Hi! I was just wondering when the new section of Hudson Way is going to be finished. (Here's a pin to the section I'm talking about: https://maps.app.goo.gl/ENYnAsavKiR1JM1o6). It's the section of road that connects the homes north of 2100 North to the warehouses. I saw that some traffic signals were added at the intersection of Hudson and Redwood and there seems to be some other work occurring but couldn't find any info about this on your website. Let me know if I can provide any further details to explain the area I'm describing! Thanks on Linkedin Email Hi! I was just wondering when the new section of Hudson Way is going to be finished. (Here's a pin to the section I'm talking about: https://maps.app.goo.gl/ENYnAsavKiR1JM1o6). It's the section of road that connects the homes north of 2100 North to the warehouses. I saw that some traffic signals were added at the intersection of Hudson and Redwood and there seems to be some other work occurring but couldn't find any info about this on your website. Let me know if I can provide any further details to explain the area I'm describing! Thanks link
Hi! I was just wondering when the new section of Hudson Way is going to be finished. (Here's a pin to the section I'm talking about: https://maps.app.goo.gl/ENYnAsavKiR1JM1o6). It's the section of road that connects the homes north of 2100 North to the warehouses. I saw that some traffic signals were added at the intersection of Hudson and Redwood and there seems to be some other work occurring but couldn't find any info about this on your website. Let me know if I can provide any further details to explain the area I'm describing! Thanks
jknaupp asked 6 months agoThe portion of Hudson Road that will connect to Redwood will be constructed by the developer. They submitted civil construction plans to the City back in October, but we haven't heard from them since. Because of this, we unfortunately don't have a timeline on when the road will be constructed and opened.
-
Share When will 1500 connect with redwood? I and neighbors have been waiting for it to open for the last 2ish years since it was done being built. Why is it I still closed off? Thank you! on Facebook Share When will 1500 connect with redwood? I and neighbors have been waiting for it to open for the last 2ish years since it was done being built. Why is it I still closed off? Thank you! on Twitter Share When will 1500 connect with redwood? I and neighbors have been waiting for it to open for the last 2ish years since it was done being built. Why is it I still closed off? Thank you! on Linkedin Email When will 1500 connect with redwood? I and neighbors have been waiting for it to open for the last 2ish years since it was done being built. Why is it I still closed off? Thank you! link
When will 1500 connect with redwood? I and neighbors have been waiting for it to open for the last 2ish years since it was done being built. Why is it I still closed off? Thank you!
Memi asked 7 months agoThe portion of 1500 N between Boston St and Redwood Rd is in Saratoga Springs and under their jurisdiction. Our understanding is there was a dispute between Saratoga Springs and the developer who built the road which has resulted in it remaining closed. We don't have any other information about it.
-
Share This is a double question. Traffic has been awful on 2100/3600 by the Maverick/Exchange/New Children's Hospital. I know they are working on a new interchange but is there any other plans for traffic lights or widening the road on 3600? It's been bad since I've moved here and that was 4 years ago. It is almost impossible to turn left out of the Exchange. Most times people have to drive into the median because there's never a chance to go. It is often bumper to bumper driving and almost being hit. I feel like this is getting more and more dangerous with the multiple ways cars are driving and coming in and out of the neighborhood/gas station etc. I know the intersection right by the new fire station has been bad as well. Is there any plans for widening in that area and adding a traffic light too? This is again off of 3600. I'm also curious as to if we know the type of businesses that are being brought by Maverick and across from Maverick in the open field off of 3600. Also across 2100 by Costa Vida/McDonalds and the new Children's hospital. Do we know what is being put in there as well? on Facebook Share This is a double question. Traffic has been awful on 2100/3600 by the Maverick/Exchange/New Children's Hospital. I know they are working on a new interchange but is there any other plans for traffic lights or widening the road on 3600? It's been bad since I've moved here and that was 4 years ago. It is almost impossible to turn left out of the Exchange. Most times people have to drive into the median because there's never a chance to go. It is often bumper to bumper driving and almost being hit. I feel like this is getting more and more dangerous with the multiple ways cars are driving and coming in and out of the neighborhood/gas station etc. I know the intersection right by the new fire station has been bad as well. Is there any plans for widening in that area and adding a traffic light too? This is again off of 3600. I'm also curious as to if we know the type of businesses that are being brought by Maverick and across from Maverick in the open field off of 3600. Also across 2100 by Costa Vida/McDonalds and the new Children's hospital. Do we know what is being put in there as well? on Twitter Share This is a double question. Traffic has been awful on 2100/3600 by the Maverick/Exchange/New Children's Hospital. I know they are working on a new interchange but is there any other plans for traffic lights or widening the road on 3600? It's been bad since I've moved here and that was 4 years ago. It is almost impossible to turn left out of the Exchange. Most times people have to drive into the median because there's never a chance to go. It is often bumper to bumper driving and almost being hit. I feel like this is getting more and more dangerous with the multiple ways cars are driving and coming in and out of the neighborhood/gas station etc. I know the intersection right by the new fire station has been bad as well. Is there any plans for widening in that area and adding a traffic light too? This is again off of 3600. I'm also curious as to if we know the type of businesses that are being brought by Maverick and across from Maverick in the open field off of 3600. Also across 2100 by Costa Vida/McDonalds and the new Children's hospital. Do we know what is being put in there as well? on Linkedin Email This is a double question. Traffic has been awful on 2100/3600 by the Maverick/Exchange/New Children's Hospital. I know they are working on a new interchange but is there any other plans for traffic lights or widening the road on 3600? It's been bad since I've moved here and that was 4 years ago. It is almost impossible to turn left out of the Exchange. Most times people have to drive into the median because there's never a chance to go. It is often bumper to bumper driving and almost being hit. I feel like this is getting more and more dangerous with the multiple ways cars are driving and coming in and out of the neighborhood/gas station etc. I know the intersection right by the new fire station has been bad as well. Is there any plans for widening in that area and adding a traffic light too? This is again off of 3600. I'm also curious as to if we know the type of businesses that are being brought by Maverick and across from Maverick in the open field off of 3600. Also across 2100 by Costa Vida/McDonalds and the new Children's hospital. Do we know what is being put in there as well? link
This is a double question. Traffic has been awful on 2100/3600 by the Maverick/Exchange/New Children's Hospital. I know they are working on a new interchange but is there any other plans for traffic lights or widening the road on 3600? It's been bad since I've moved here and that was 4 years ago. It is almost impossible to turn left out of the Exchange. Most times people have to drive into the median because there's never a chance to go. It is often bumper to bumper driving and almost being hit. I feel like this is getting more and more dangerous with the multiple ways cars are driving and coming in and out of the neighborhood/gas station etc. I know the intersection right by the new fire station has been bad as well. Is there any plans for widening in that area and adding a traffic light too? This is again off of 3600. I'm also curious as to if we know the type of businesses that are being brought by Maverick and across from Maverick in the open field off of 3600. Also across 2100 by Costa Vida/McDonalds and the new Children's hospital. Do we know what is being put in there as well?
ashbri94 asked 8 months agoOne reason traffic has gotten worse on 3600 W is because 2300 W is closed for a roadway widening project. A portion of the traffic that was using 2300 W is using 3600 W now. There will be some relief when 2300 W reopens. We do recognize that traffic volumes are growing outside of the 2300 W closure and are working to make improvements.
There are plans for a traffic signals at Hardman Way 3600 W and at 1500 N 3600 W. The Hardman Way traffic signal will be installed with adjacent development that is currently working through the city for approval. The design of a traffic signal at 1500 N is completed and we are working to obtain needed property on the northeast corner from Rocky Mountain Power.
The Transportation Master Plan (https://www.lehi-ut.gov/wp-content/uploads/2023/02/Master_Transportation_Plan_11x17-minor-rev.-Jan-23-2023.pdf) has 3600 W as a Major Arterial which will have 5 lanes (2 northbound, 2 southbound, and a center turn lane). It is primarily being widened piece by piece as adjacent land develops. We do have plans for some widening to the east between Hardman Way and the Maverik gas station this summer.
We only know a few of the businesses that are going in in that area. There will be a grocery store going in on the empty field across from the Maverick. There will also be a 7-Eleven on the corner of 3600 West and Waterbury in Holbrook Farms. Other than that we don't know the exact businesses that are going in. The area is zoned Commercial, so we expect some food establishments and retail buildings.
-
Share Is there ever going to be another way for people to get out of Jordan Willow subdivision??? Willow Ln has become Joke. Thousands of vehicles non stop, all day, everyday. It has become a major highway!!!!!!!!!! The SPEEDING and the NOISE is unbelievable. There is days where I sit in my driveway for 5 minutes waiting just to pull out into Willow Ln. It's a subdivision, I don't see this problem in other subdivisions? Please tell me it's at least a thought. on Facebook Share Is there ever going to be another way for people to get out of Jordan Willow subdivision??? Willow Ln has become Joke. Thousands of vehicles non stop, all day, everyday. It has become a major highway!!!!!!!!!! The SPEEDING and the NOISE is unbelievable. There is days where I sit in my driveway for 5 minutes waiting just to pull out into Willow Ln. It's a subdivision, I don't see this problem in other subdivisions? Please tell me it's at least a thought. on Twitter Share Is there ever going to be another way for people to get out of Jordan Willow subdivision??? Willow Ln has become Joke. Thousands of vehicles non stop, all day, everyday. It has become a major highway!!!!!!!!!! The SPEEDING and the NOISE is unbelievable. There is days where I sit in my driveway for 5 minutes waiting just to pull out into Willow Ln. It's a subdivision, I don't see this problem in other subdivisions? Please tell me it's at least a thought. on Linkedin Email Is there ever going to be another way for people to get out of Jordan Willow subdivision??? Willow Ln has become Joke. Thousands of vehicles non stop, all day, everyday. It has become a major highway!!!!!!!!!! The SPEEDING and the NOISE is unbelievable. There is days where I sit in my driveway for 5 minutes waiting just to pull out into Willow Ln. It's a subdivision, I don't see this problem in other subdivisions? Please tell me it's at least a thought. link
Is there ever going to be another way for people to get out of Jordan Willow subdivision??? Willow Ln has become Joke. Thousands of vehicles non stop, all day, everyday. It has become a major highway!!!!!!!!!! The SPEEDING and the NOISE is unbelievable. There is days where I sit in my driveway for 5 minutes waiting just to pull out into Willow Ln. It's a subdivision, I don't see this problem in other subdivisions? Please tell me it's at least a thought.
Scott14 asked 9 months agoLehi and Saratoga Springs have a three-way corridor agreement with UDOT for a new traffic signal at approximately 2900 W on Pioneer Crossing (1/2 mile west of the 2300 W traffic signal). A road connection from that traffic signal will extend into the Jordan Willows subdivision allowing direct access to Pioneer Crossing. The timing of this is driven by when the adjacent land is developed. It should give relief to the traffic you're experiencing on Willow Ln.
There is also an upcoming project to widen 2300 W between Main St and Pioneer Crossing to 5 lanes (2 northbound, 2 southbound, and a center turn lane). This is separate from the current project underway widening 2300 W north of Main St to 2100 N. This project includes the installation of a traffic signal at 700 S 2300 W. We also expect a future traffic signal at Grays Dr 2300 W, the project will install pole foundations in anticipation of the future traffic signal. A new road heading west from that intersection is planned that could serve traffic from Jordan Willows as well. This project is expected to start in 2027.
We understand you're in a difficult situation and are sympathetic. Relief is coming and there are plans are in place. We appreciate your patience as we work to bring these improvements into reality.
-
Share Can you share the final plan for Northridge Park? on Facebook Share Can you share the final plan for Northridge Park? on Twitter Share Can you share the final plan for Northridge Park? on Linkedin Email Can you share the final plan for Northridge Park? link
Can you share the final plan for Northridge Park?
rrawat asked 9 months agoYes, see the image below. You also can contact Brittney Harris bharris@lehi-ut.gov for a PDF