24 April 2024

Groundbreaking Ceremony

20 May 2024

Major Construction Begins

Fencing will be placed around the construction site and major construction will begin. 

28 May 2024

Begin Installing Piers

The new building requires support piers in the ground because of the makeup of the ground materials. Those will be installed before the foundation can be poured. 

August 2024

Library Moved to Temporary Location

07 August 2024

Foundation Complete

September 2024

Library Demolished for Construction of New Civic Center.

19 September 2024

Start Erecting Steel

20 November 2024

Level Two Slab Poured

20 December 2024

Level Three Slab Poured

15 January 2025

Steel Complete

04 March 2025

Roof Complete

September 2025

Expected Completion Date